Blending the Clocktower Brick at Bronson Place
The brick on this community went up off color, worst of all on the clocktower everybody looks at. The company that made the brick hired the correction rather than see it torn out. It was photographed again twenty-five years later and certified then.
1994
What was wrong
Discoloration, and most of it high up where nobody could miss it. The file names the place: a lot of discoloration in the clocktower and surrounding areas. Under that sat a second fault, directional texture, meaning the faces took the light differently depending on which way each unit had been laid.
The brick manufacturer hired the work. Not the owner and not the mason: the company that supplied the brick treated the color of a finished community as its own problem.
What was done
Mineral stain, brushed on by hand, unit by unit, in both directions at once. The phrase in the file is lightened and darkened brick to create a better match, which is the part most people do not expect. Correcting a blend means bringing some units down as well as bringing others up. It took over three weeks.
2019, twenty-five years on
-
2019
View this photo larger
-
25 Years After
View this photo larger
-
2019
View this photo larger
-
After, 2019
View this photo larger
What twenty-five years prove
Same clocktower, same walls, and a blend that is still the blend it was mixed to. On the certification scale that is Platinum, the top band, which covers twenty years and over. As of 2026 the work is thirty-two years old, and the 2019 certification is the most recent record on it.
The signed file
Every certified job gets the same form, signed on the day someone goes back to the building. This is the one for case 091, transcribed beside the scan so it can be read on a phone and by a search engine.
View the signed form full size
- Project name
- Bronson Place (1994)
- Level
- Platinum, the top band. The scale runs Bronze at seven to nine years, Silver at ten and over, Gold at fifteen and over, Platinum at twenty and over.
- Hired by
- The brick manufacturer
- Reason for project
- Complaint or problem
- Issue
- "A lot of discoloration in the clocktower and surrounding areas."
- What was corrected
- "MCI lightened and darkened brick to create a better match."
- Storyline
- "A lot of directional texture problems and also color issues that we worked on for over three weeks to create a better blend."
- Authorized
- Donald A. Foster, signed, dated 2019