Matching a Second Story Addition on a Pennsylvania Church
This church added a second story, and even the closest brick available did not match the building below it. The addition was stained in 2004, along with some of the entrances. It was photographed again fifteen years later and certified Gold.
2004
-
Before, 2004
View this photo larger
-
Before, 2004
View this photo larger
-
During, 2004
View this photo larger
-
During, 2004
View this photo larger
-
During, 2004
View this photo larger
-
During, 2004
View this photo larger
-
After, 2004
View this photo larger
What was wrong
The cause on the form is an addition, not a complaint. The closest brick available was laid, and it still read noticeably off color against the original walls, one range sitting on another. The church itself hired the correction.
What was done
A test panel first. A translucent stain keeps the tone variation of the brick, so the panel is what proves the custom blend before the walls are touched, or sends it back for a different mix. Then every brick on the second story, from a lift and from ladders, plus some of the entrances.
2019, fifteen years on
-
After, 2019
View this photo larger
-
After, 2019
View this photo larger
-
After, 2019
View this photo larger
-
After, 2019
View this photo larger
-
After, 2019
View this photo larger
What fifteen years prove
No fading, blistering, cracking or flaking after fifteen years, in the file's own words, and the stained brick has held up as well as the unstained brick. Gold on the certification scale covers fifteen years and over. As of 2026 the work is twenty-two years old, and the 2019 certification is the most recent record on it.
The signed file
Every certified job gets the same form, signed on the day someone goes back to the building. This is the one for case 156, transcribed beside the form so it can be read on a phone and by a search engine.
View the signed form full size
- Project name
- Church, Pennsylvania (2004)
- Level
- Gold. The scale runs Bronze at seven to nine years, Silver at ten and over, Gold at fifteen and over, Platinum at twenty and over.
- Hired by
- Business or corporation
- Reason for project
- Addition or makeover
- Background
- "When this church built a second story, the brick on the expansion did not match the original building."
- Actions taken
- "We stained 100% of the brick on the second story, and also stained some entrances."
- Detail of events
- "What a project! They had the closest match they could find, but it wasn't close enough, so we were called in. The brick stained in 2004 have held up just as well as the unstained brick!"
- Authorized
- Donald A. Foster, signed, dated 2020
Your Project, Documented for Decades
Every job we stain enters the same discipline: photographed, revisited, re-photographed.
Request a Quote