Blending the Soldier Course on an Ohio Shopping Mall
The soldier brick on this mall was rejected for carrying too much color range. The company that made the brick paid to have it blended rather than pulled out. Two applications and three days later the architect approved the range, and it was photographed again twenty-three years on.
1996
What was wrong
The soldier courses were rejected. Nothing had failed and nothing was dirty; the upright units carried more variation than the banding would take. The file puts it in eleven words: the soldier brick was rejected because there was too much range.
It was hired by the brick manufacturer, not the owner and not the mason. The company that supplied the brick paid for staining rather than replacement.
What was done
Mineral stain, brushed on by hand, unit by unit across the two bands. The file records two applications over three days, after which the architect approved the color range. The phrase in the file is blended the brick for an acceptable range.
2019, twenty-three years on
-
2019
View this photo larger
-
2019
View this photo larger
-
2019
View this photo larger
-
23 Years After
View this photo larger
What twenty-three years prove
Same banding, and a range that is the range the architect signed off. On the certification scale that is Platinum, which covers twenty years and over. The file is plain about what did not last: the brick wall system has some issues but the staining remains intact. As of 2026 the work is thirty years old.
The signed file
Every certified job gets the same form, signed on the day someone goes back to the building. This is the one for case 260, transcribed beside the scan so it can be read on a phone and by a search engine.
View the signed form full size
- Project name
- OH Mall (1996)
- Level
- Platinum. The scale runs Bronze at seven to nine years, Silver at ten and over, Gold at fifteen and over, Platinum at twenty and over.
- Hired by
- The brick manufacturer
- Reason for project
- Complaint or problem
- Issue
- "The soldier brick was rejected because there was too much range."
- What was corrected
- "We blended the brick for an acceptable range."
- Storyline
- "Two applications and three days later the color range was approved by the architect. 23 years later the brick wall system has some issues but the staining remains intact."
- Authorized
- Donald A. Foster, signed, dated 2019