Darkening the Light Run on a Canton High Rise
The brick for this building arrived in two runs and one of them was lighter. The company that made the brick paid to have the light units darkened rather than have the wall taken down. It was photographed again twenty-five years later and certified then.
1994
What was wrong
One order, two runs of brick, and one run lighter than the other. Nothing had failed and nothing was dirty. The wall went up striped, with blotchy areas where the two runs met.
It was hired by the brick manufacturer, not the owner and not the mason. A brick company decided the color of a finished high rise it had supplied was its own problem, and paid for staining over tear-out.
What was done
Mineral stain, brushed on by hand. Not one color over the whole building: only the light run was taken down to meet the darker one, which is why the banding and the darker headers still read on the finished wall. The phrase in the file is darkened the light brick.
2019, twenty-five years on
-
2019
View this photo larger
-
25 Years After
View this photo larger
-
2019
View this photo larger
-
2019
View this photo larger
-
2019
View this photo larger
What twenty-five years prove
Same building, same brick, and a wall that reads as one color. On the certification scale that is Platinum, which covers twenty years and over and is the top of the scale. The six 2019 frames were taken between 12:18 and 12:21 on 20 July 2019, one walk around the building on the day the form was signed. As of 2026 the work is thirty-two years old, and the 2019 certification is the most recent record on it.
The signed file
Every certified job gets the same form, signed on the day someone goes back to the building. This is the one for case 082, transcribed beside the scan so it can be read on a phone and by a search engine.
View the signed form full size
- Project name
- Canton High Rise (1994)
- Level
- Platinum. The scale runs Bronze at seven to nine years, Silver at ten and over, Gold at fifteen and over, Platinum at twenty and over.
- Hired by
- The brick manufacturer
- Reason for project
- Complaint or problem
- Issue
- "Brick MFG had to use two different runs of brick on this project and one run was lighter than the other."
- What was corrected
- "Darkened the light brick."
- Storyline
- "Stained some of the light stripes and blotchy areas on the building due to the color difference of the two different runs of brick."
- Authorized
- Donald A. Foster, signed, dated 20 July 2019